Delhi Commonwealth Games 2010 – The Con Games
Delhi Commonwealth Games LogoThe Commonwealth Games, scheduled to be held between 3rd – 14th October in Delhi, will be the largest multi-sport event to be held in India after the Asian Games in 1951 and 1982. As many as 72 nations will participate in the games. This will be the second time, the Commonwealth Games will be held in Asia. Therefore, the event is significant and a big moment for India. The city is under siege from multiple agencies, 21 in total, all working at cross purposes and stepping on each others toes while the mad scramble to give the Capital a face-lift clashes with the frantic construction to get the stadia and other Games-related venues ready on time. The monsoon downpours have only made matters worse, leading to flooded venues, blocked drainage, leaking ceilings, burst water pipes and seepage everywhere. Here’s a reality check.
1. The Jawaharlal Nehru Stadium, which is to host all key events including athletics and weight-lifting, and the opening and closing ceremonies, is struggling to meet its July 31 deadline. Ten days before the scheduled handover to the Organizing Committee (OC), the stadium resembles a dust bowl, with open drains and piles of rubble all around and the approach roads still in the early stages of construction. As things stand, only the main arena would be ready by the deadline, with the peripheral work to continue till mid-September, barely two weeks before the opening ceremony.
2. The shooting range at Kadarpur in Gurgaon, an official Games venue, has “collapsed”. Inaugurated barely two months ago by Sports Minister M.S. Gill, the range had even hosted a test event for the Games but has now self-destructed after the rains. On July 8, dig and Manager (Sports), Central Reserve Police Force (CRPF), M.C. Panwar (the Range is built on CRPF land) wrote a desperate letter to top sports ministry officials. “Due to the incessant rains on the night of July 4 and 7, the various embankments on the range have collapsed and extensive damages (sic) have been caused. The grassy expanse of lawn overhead the first box culvert has been washed away along with the side foot-tracks.”
3. At the Yamuna Sports Complex, where the table tennis events will be staged, the false ceiling collapsed and the wooden flooring has been badly damaged because of waterlogging. Both will need to be replaced. The new deadline for completion is now first week of September, one month later than the original deadline of August 1.
4. The Siri Fort badminton complex, where World Number 2 Saina Nehwal will be India’s biggest medal hope, faces the same problem with the wooden floor having buckled due to seepage. The entire floor will have to be relaid.
5. The “new” Dr S.P. Mukherjee Swimming Complex built at a cost of Rs 377 crore, was inaugurated last week with parts of the complex still to be completed. During the inauguration, a waterpipe malfunction sprayed water on the people present there. The walls are already marked by seepage.
6. The rains have led to flooding the newly constructed Velodrome at the Indira Gandhi Stadium, a fully air-conditioned indoor timber track, built at a cost of Rs 150 crore.
7. The Talkatora Boxing Stadium has major problems with flooding inside because of leakage, while there was more than a foot of water all around outside.
8. The vital timing, scoring, result (TSR) equipment will only be commissioned 10 days before the start of the Games, a ridiculous state of affairs since glitches and settings take time to be tested and ironed out.
9. Every approach road to the venues is dug up, waterlogged, minus pavements and dividers, and the construction debris has entered the drainage system leading to flooding each time it rains, even for a brief spell.
10. The Major Dhyan Chand Stadium, venue for hockey, was inaugurated on January 24, after missing the original deadline by four months. Costing Rs 262 crore, 50 crore more than was budgeted, the peripheral work is still on.
11. The catering contracts for the Games venues was canceled last week, meaning fresh bids will have to be submitted and approved, leaving no time for the eventual caterers to prepare and set up operations.
12. As if that wasn’t enough, some of the world’s best athletes, including Olympic and world champion sprinter Usain Bolt, have pulled out of the Games robbing it of much of its luster and led to an unseemly and very public war of words between Gill and Commonwealth Games Organizing Committee Chairman Suresh Kalmadi.
The stadiums ares not the only worry. The Games Village is not ready either. Built at a cost of nearly Rs 1,100 crore, the first deadline was December 2009, later shifted to March 2010 and finally to July 31. The work in the Village slowed down in December 2008 when Emaar MGF claimed that it had no money due to the global meltdown. The DDA, its PPP partner, had to cough up Rs 766 crore as a bailout package. The eviction of 3,000 students from their hostels indicates that the Village will not be ready and last minute alternate arrangements are being made.
In fact, there is not a single aspect, which the OC or the Sports Ministry can claim has been completed to satisfaction. The OC is still not sure how it will feed the sports persons, athletes, officials and referees outside the Games Village. With more than 30 lakh meals expected to be cooked during the fortnight of the Games, it’s one of the most important functional areas of the event.