Last checked HResidence building progress in early Nov 2012, saw Tower A Top-Up, partly painted. Tower B reach 10th Floor & another 12 Floor to go. This will take them at least till Feb-Apr to Top Up Tower B. Owner, Buyer & Seller, do come in here to share
The residencial unit starts from 3rd floor... so it has less than 10 floors to go...
The background. Is it a lake?
Tower B should be up to 22nd Floor, according to Plan ?
Last checked HResidence building progress in early Nov 2012, saw Tower A Top-Up, partly painted. Tower B reach 10th Floor & another 12 Floor to go. This will take them at least till Feb-Apr to Top Up Tower B.
Had been there yesterday, they were building 14th & 15th floor (as I count fr 3rd floor).
Fr my observation, their building pace is 1-2 wk per floor. & my estimation is another 12 weeks to reach e Top!
Hope it will Top-up b4 Chinese New Year (asap, as I'm anxious & excited)