Have anyone actually try to visualise how 9000 condo unit in a project will look like?
The Sail @ Marina Bay is 1,111 units.
You put 8 times The Sail @ Marina Bay you will get 8,888 units.
That is how huge the projects is.
And now imagine you trying to get a tenant.....:p
And had anyone also ever imagine how are they going to build 9,000 units in one go?
What kind of resources the need do perform this task?
They should be needing a work force of nearly 2,000, from architects and engineers to their site coordinators and of cos workers and technicians like bricklayers, plumbers, carpenters, electricians, crane operators etc.
Just floor and wall tiling to the 9,000 units alone, even if they can speed tile 20 units per working day, they need almost 2 years just to do the tiling works!
During the sales carnival, some people asked about the proposed work schedule like when is piling works commencing, no one can give an answer.
Anyone knows when they will start piling? Unlikely this year end cos reclaimation works still in progress, so next year or 2015??
Very very sceptical that project can completed by the 2018 as promised!!