Feds say Pratt & Whitney late delivering engines for F-35 fighter jet
By Tony Capaccio
| Hartford Courant |
Jul 02, 2019 | 5:10 PM
An Israeli F-35 fighter jet performs during an air show at the graduation ceremony of Israeli pilots in the Hatzerim Israeli Air Force base in the Negev desert, near the southern Israeli city of Beer Sheva, on June 27, 2019. (JACK GUEZ/AFP/Getty Images) (JACK GUEZ/Getty)
A federal agency says that Pratt & Whitney is chronically late delivering engines for the Pentagon’s costliest program, the F-35, raising questions about whether the company is ready for a surge to full-rate production scheduled for next year.
Pratt remains under a previously unreported “Corrective Action Request” from the Defense Contract Management Agency that cites “poor delivery performance” on its current batch of engines for the fighter jet, including for the most complicated version used by the Marine Corps and the U.K. for vertical takeoffs and landings. Pratt & Whitney is a subsidiary of Farmington-based United Technologies Corp.
Pratt & Whitney president to retire next year as UTC and Raytheon combine in aerospace and defense merger »
The agency’s action is likely to be watched not only by the Pentagon and international buyers of the F-35 but also by shareholders and investors assessing United Technologies’ planned merger with Raytheon Co., which would fortify the combined company’s standing as one of the top U.S. defense contractors.
The F-35 engines would be one of the new company’s top revenue producers. The company, which is the sole supplier of engines for the fighter built by Lockheed Martin Corp., must demonstrate by year-end that it has delivered on promised improvements to solve the problems that led to the agency’s formal request in December, spokesman Mark Woodbury said in a statement outlining the issues.
[Business] City will move forward with Downtown North development after jury backs Hartford’s decision to fire Dunkin’ Donuts Park developer in 2016 »
The $428 billion F-35 program is scheduled for approval next year to enter full-rate production, the most lucrative phase of a weapons program for contractors. The decision is contingent on an assessment during the aircraft’s current round of intensive combat testing that it’s effective and can be maintained.
Of the $428 billion, as much as $66 billion is to be spent on at least 2,470 engines -- designated the F135 -- for U.S. jets, including $53.4 billion in procurement, according to the Defense Department’s latest Selected Acquisition Report on the F-35.
Pentagon budget documents indicate the engine program is valued at about $2 billion annually for Pratt, according to Bloomberg Intelligence analyst Douglas Rothacker.
John Thomas, a spokesman for Pratt, said in an emailed statement that “we take seriously our responsibility to meet F135 production commitments. The corrective action plan submitted earlier this year lays out how we are doing that. Over the past year, we have invested more than $200 million for additional capacity, and currently have over 100 Pratt & Whitney employees deployed to our supplier facilities in support of production obligations.”
Pratt & Whitney President Bob Leduc underscored the engine’s revenue potential to analysts June 17 at the Paris Air Show.
[Business] City will move forward with Downtown North development after jury backs Hartford’s decision to fire Dunkin’ Donuts Park developer in 2016 »
“So another way to think about the F135 is a year ago we made about eight engines a month,” he said. “Right now we are between 13 and 14 engines a month. But when you think about the F135, it’s 16 engines a month for the next 30 years. There will be over 4,000 of these airplanes when it’s all said and done,” including foreign sales.
The primary issues resulting in late engine deliveries “have been related to supply-chain capacity, material shortages” and production issues, according to the contract management agency.
“Engine test failures due to high vibrations and foreign object debris continues to plague” production, the agency said in an internal quarterly assessment for January through March.
Deliveries of the Marine Corps model engines “have been consistently late,” it said.
As of early June, Pratt & Whitney was contractually required to deliver 108 engines in the latest production contract, the program’s 11th. Of the 90 delivered, 88 were “late by an average of 40 days,” Woodbury said in his statement.
The Pentagon is close to finalizing the award of the 12th and largest F-35 contract to date with Lockheed and Pratt.
The current delays add to Pratt & Whitney’s spotty track record. Even as deliveries increased to 81 in 2018 from 48 in 2012, 86 percent of those were delivered late, up from 48 percent in late 2017, according to an April report from the Government Accountability Office.
Asked whether the contract management agency has confidence Pratt will be ready for a full-production decision, Woodbury said the agency is monitoring milestones in Pratt’s corrective action plan and needs to see progress before making that judgment.
The agency’s assessment said that in light of Pratt & Whitney’s track record it believes the company “will encounter issues keeping up with demand for any future low-rate and full- rate production contract” that increases quantities.
https://www.bloomberg.com/news/arti...gies-pratt-slow-on-f-35-engines-pentagon-says
United Technologies’ F-35 Engines Chronically Late, Pentagon Says
By
Anthony Capaccio
July 2, 2019, 4:00 PM GMT+8
LISTEN TO ARTICLE
4:22
SHARE THIS ARTICLE
Share
Tweet
Post
Email
In this article
UTX
UNITED TECH CORP
133.00
USD
+1.04+0.79%
LMT
LOCKHEED MARTIN
370.38
USD
+2.81+0.76%
RTN
RAYTHEON CO
173.45
USD
+0.65+0.38%
United Technologies Corp.’s Pratt & Whitney unit is chronically late delivering engines for the Pentagon’s costliest program, the F-35, raising questions about whether the company is ready for a surge to full-rate production scheduled for next year.
Pratt remains under a previously unreported “Corrective Action Request” from the Defense Contract Management Agency that cites “poor delivery performance” on its current batch of engines for the fighter jet, including for the most complicated version used by the Marine Corps and the U.K. for vertical takeoffs and landings.
The agency’s action is likely to be watched not only by the Pentagon and international buyers of the F-35 but also by shareholders and investors assessing United Technologies’ planned merger with Raytheon Co., which would fortify the combined company’s standing as one of the top U.S. defense contractors. The F-35 engines would be one of the new company’s top revenue producers.
The company, which is the sole supplier of engines for the fighter built by Lockheed Martin Corp., must demonstrate by year-end that it has delivered on promised improvements to solve the problems that led to the agency’s formal request in December, spokesman Mark Woodbury said in a statement outlining the issues.
An F-35
Photographer: Eric Baradat/AFP via Getty Images
Full Production
The $428 billion F-35 program is scheduled for approval next year to enter full-rate production, the most lucrative phase of a weapons program for contractors. The decision is contingent on an assessment during the aircraft’s current round of intensive combat testing that it’s effective and can be maintained.
Of the $428 billion, as much as $66 billion is to be spent on at least 2,470 engines -- designated the F135 -- for U.S. jets, including $53.4 billion in procurement, according to the Defense Department’s latest Selected Acquisition Report on the F-35.
Pentagon budget documents indicate the engine program is valued at about $2 billion annually for Pratt, according to Bloomberg Intelligence analyst Douglas Rothacker.
John Thomas, a spokesman for Pratt, said in an emailed statement that “we take seriously our responsibility to meet F135 production commitments. The corrective action plan submitted earlier this year lays out how we are doing that. Over the past year, we have invested more than $200 million for additional capacity, and currently have over 100 Pratt & Whitney employees deployed to our supplier facilities in support of production obligations.”
Revenue Potential
Pratt & Whitney President Bob Leduc underscored the engine’s revenue potential to analysts June 17 at the Paris Air Show.
“So another way to think about the F135 is a year ago we made about eight engines a month,” he said. “Right now we are between 13 and 14 engines a month. But when you think about the F135, it’s 16 engines a month for the next 30 years. There will be over 4,000 of these airplanes when it’s all said and done,” including foreign sales.
The primary issues resulting in late engine deliveries “have been related to supply-chain capacity, material shortages” and production issues, according to the contract management agency.
“Engine test failures due to high vibrations and foreign object debris continues to plague” production, the agency said in an internal quarterly assessment for January through March. Deliveries of the Marine Corps model engines “have been consistently late,” it said.
As of early June, Pratt & Whitney was contractually required to deliver 108 engines in the latest production contract, the program’s 11th. Of the 90 delivered, 88 were “late by an average of 40 days,” Woodbury said in his statement. The Pentagon is close to finalizing the award of the 12th and largest F-35 contract to date with Lockheed and Pratt.
Spotty Record
The current delays add to Pratt & Whitney’s spotty track record. Even as deliveries increased to 81 in 2018 from 48 in 2012, 86% of those were delivered late, up from 48% in late 2017, according to an April report from the Government Accountability Office.
Asked whether the contract management agency has confidence Pratt will be ready for a full-production decision, Woodbury said the agency is monitoring milestones in Pratt’s corrective action plan and needs to see progress before making that judgment.
The agency’s assessment said that in light of Pratt & Whitney’s track record it believes the company “will encounter issues keeping up with demand for any future low-rate and full-rate production contract” that increases quantities.
— With assistance by Rick Clough
http://www.defense-aerospace.com/ar...the-long-history-of-f_35-engine-problems.html
Home
Releases
Reports
Word for word
Features
AFP News
Order
F-35 Grounded After New F-135 Engine Problems
(Source: JSFNieuws.nl; published February 22, 2013)
By Johan Boeder
There have been several instances of turbine blades breaking off on the Pratt & Whitney F135 engine. Shown here are several broken blades during the first known incident, on Aug. 30, 2007, which ultimately led to the engine’s re-design in 2008. (photo P&W)
KESTEREN, Netherlands --- On Thursday, February 21, 2013, the Pentagon Friday ordered the grounding for all F-35 aircraft, after a routine check at the Edwards Air Force Base revealed a crack in a low pressure turbine blade in the engine of an F-35A.
This is but the latest incident concerning the Pratt & Whitney F135 engine, as during 2007-2009 repeated problems with turbine blades led to significant delays in the test program and a partial redesign of certain parts of the engine.
On February 19, 2013 a routine inspection took place of a Pratt & Whitney F135 engine at Edwards AFB, USA. During the inspection using a borescope, there were indications that there was a crack in a LPT turbine blade. It was confirmed after further investigation. The turbine blade is sent to Pratt & Whitney in Middletown (CT), USA for further investigation.
Statements from JSF Program Office
The F-35 JSF Program Office said in a Feb. 22 statement to the press: “It is too early to know the fleet-wide impact of this finding, however as a precautionary measure, all F-35 flight operations have been suspended until the investigation is complete and the cause of the blade crack is fully understood. The F-35 Joint Program Office is working closely with Pratt & Whitney and Lockheed Martin at all F-35 locations to ensure the integrity of the engine, and to return the fleet safely to flight as soon as possible.”
Lt. Gen. Chris Bogdan, head of the JSF Program Office, suggested in a briefing in Australia that if the crack's cause was as straightforward as a foreign object striking the turbine, or a basic manufacturing defect, “I could foresee the airplane back in the air in the next week or two.”
Bogdan added that “If it's more than that, then we have to look at what the risk is to the fleet,” adding than a verdict on the cracking's cause was expected "by the end of this week", Reuters reported from Melbourne.
Some facts about what happened
It was a F-135 engine with 700 hours, of which 409 flight hours. The aircraft was the F-35A test aircraft AF-2. The half-inch wide crack was found in a turbine blade of the low pressure turbine section. This makes it unlikely that it is caused by so-called FOD (Foreign Object Damage), such as a bird strike, because such an object has to pass the Fan Section (3 stages) Compressor Section (6 stages), combustor and high pressure turbine section before reaching the low pressure turbine section.
Cracks in turbine blades in the low pressure turbine section usually are caused by high thermal or other stressing loads of the turbine blades. The forces in the 40.000 lb (about 29.000 hp) engine are enormous. A grounding after such a discovery usually takes relatively short (e.g. one week), normally a manufacturing error or some incident is the root cause.
Until then, for safety reasons a grounding may be the standard procedure. Reuters reported Feb 24 that “In fact, two jets were airborne at air bases in Maryland and Arizona and had to be recalled, said one of the sources.” At this moment, all 51 F-35s, of all versions, in use at several airfields to support the test and training program, are grounded.
Long history of engine problems since 2006
It cannot be excluded that the root cause of the current problem is more structural than a simple manufacturing error or an isolated incident. Since 2006 there had been a series of engine problems with the F-135 engine.
In May 2006, Aviation Week reporter David A. Fulghum wrote a detailed article “Joint Strike Fighter F135 Engine Burns Hotter Than Desired” and described the risk of a shorter engine life or engine damage caused by higher than expected temperatures on the F-135 engine.
In August 2007 and February 2008 there were serious problems. Turbine blades broke off suddenly by a form of metal fatigue. The cause was sought in a combination of factors.
On 30 August 2007 in test engine FX634, after 122 hours of testing, a turbine blade in the 3rd LPT stage broke off completely. On February 4, 2008 something similar happened to engine FTE06, also in the 3rd LPT stage, after 19 hours.
These problems with the engine contributed significantly to the delays in the JSF test program for the period 2007-2008.
Redesign of the engine in 2008
In early 2008, an engine, the FX640 ground test engine, was equipped with numerous sensors and instruments. On April 21, 2008 a test process was started to find the cause of the problem. Through a detailed test plan the forces and tensions that arise in the engine were mapped in different power ranges.
At that moment it seemed to be primarily an issue of the F-35B STOVL (vertical landing) version. The cracks in the turbine blades were created in exactly the same place, and seemed to occur when switching from forward to vertical drive. Later in 2008, the results became available. The blade cracks seemed to have been caused by certain vibrations that triggered a material failure.
This led to a redesign of a number of elements in the engine. One of the upgrades was a change of the distance between the turbine blades. After the redesign the engine was retested and recertified. At the end of 2008 Pratt & Whitney issued a press statement, saying that they were convinced that the problems were solved.
(UPDATE: A link to a July 22, 2008 briefing by Pratt & Whitney on F135 blade failures was removed on Feb. 28 at the request of the F-35 Joint Program Office. The "information in those slides has the potential to compromise the safety of our pilots," the request stated -- Editor.)
In 2009, problems with redesigned engine
In July 2009, the then head of the JSF Program Office, Marine Corps Maj. Gen. David R. Heinz, was still was not happy with the F-135 problems. He told the press: “The problems include too many individual blades that fail to meet specifications, as well as combined “stack-ups” of blades that fail early. I’m not satisfied with the rates that I’m getting.”
A few days later he was ordered by the Pentagon not to comment publicly on problems with the F-135 engine.
In September 2009, serious engine problems were again revealed during testing of the Pratt & Whitney F-135 engine. At a crucial moment in the debate in the U.S. Congress on the choice of two competing engine types (the Pentagon wanted to axe the alternate engine (the GE / Rolls Royce F-136), a Pratt & Whitney F-135 engine broke down. Again, the cause seemed to lie in broken turbine blades. However, this time the same problem occurred in the new, redesigned engine with redesigned turbine blades.
Engine problems continue until now
After the problems in 2009, officials no longer publicly commented about the engine problems. Also there were no indications that there actually were problems with the engine or that there were any reliability issues.
In April 2011, however, Admiral Venlet, the then Head of JSF Program Office, told reporters that some engine problems were impacting on the delivery schedule.
The grounding last week puts the engine back in the publicity spotlight. However, this time it is not the complex F-35B STOVL version, but the much simpler engine in the F-35A, the Air Force version, that failed, which has led some observers to speculate that the problem could be more deeply ingrained in the engine’s design.
History of previous F-35 groundings
May 2007: The first incident was recorded in May 2007, when the F-35A prototype AA-1 experienced an electrical short that disabled flight controls on the horizontal stabliser. A grounding was ordered and continued until December 2007, due to time needed to redesign several parts of the 270-volt electrical system and F-135 engine problems.
July 2008: On July 23, 2008, both flying F-35 prototypes were grounded after problems were detected with ground cooling fan electrical circuitry, DCMA reported on Aug 18, 2008 that tests were delayed as a result of testing anomalies on the 28 Volt and 270 Volt Battery Charger/Controller Unit, the Electrical Distribution Unit and the Power Distribution Unit. It was due to design problems. Flights were resumed first week of September-2008.
December 2008: On Dec 12, 2008 the F-35 was grounded again as a result of engine and ejection seat anomalies. Seat anomalies were observed in ejection seat sequence during an escape system test on Nov. 20, 2008. It took nearly 3 months to solve the problems and aircraft AA-1 did not return to the skies until Feb. 24, 2009.
May 2009: The F-35 fleet didn’t fly between May 7, 2009 (84th flight of prototype AA-1) and Jun 23, 2009. No comments were available from JPO or L-M.
October 2010: F-35 fleet grounded after the fuel pump shut down above 10,000ft (3,050m). The problem was caused by a software bug.
March 2011: The entire F-35 fleet was grounded some weeks after test aircraft AF-4 experienced a dual generator failure. After both generators shut down in flight, the IPP activated and allowed the F-35’s flight control system to continue functioning. The problem was traced to faulty maintenance handling.
June 2011: Carrier-based F-35C suspended from flying after engineers at NAS Patuxent River discovered a software problem that could have affected the flight control surfaces. Grounding was from 17 June until 23 June, 2011.
August 2011: A precautionary grounding of all 20 F-35s that had reached flying status was ordered Aug. 3, 2011 after a valve in the Integrated Power Package (IPP) of F-35A test aircraft AF-4 failed. On 18 August 2011 the flight ban was lifted to allow monitored operations. A permanent resolution would be installed later.
January 2012: 15 Lockheed Martin F-35s are grounded for about 12 days to repack improperly installed parachutes (reversed 180 degrees from design). The grounded aircraft are equipped with new versions of the Martin Baker US16E ejection seat, designated as -21 and -23.
January 2013: The F-35B STOVL variant was grounded Jan 18, 2013 after detection of a failure of a fueldraulic line in the aircraft's propulsion system. The Pentagon cleared all 25 F-35B aircraft to resume flight tests on February 12, 2013. Problem caused by a manufacturing quality problem (wrongly crimped fuel line).
February 2013: On Feb. 21, 2013, the Pentagon ordered a grounding for all F-35 aircraft, after a routine check at the Edwards Air Force Base revealed a crack in a low pressure turbine blade in an engines of a F-35A.
-ends-
Feds say Pratt & Whitney late delivering engines for F-35 fighter jet
By Tony Capaccio
| Hartford Courant |
Jul 02, 2019 | 5:10 PM
An Israeli F-35 fighter jet performs during an air show at the graduation ceremony of Israeli pilots in the Hatzerim Israeli Air Force base in the Negev desert, near the southern Israeli city of Beer Sheva, on June 27, 2019. (JACK GUEZ/AFP/Getty Images) (JACK GUEZ/Getty)
A federal agency says that Pratt & Whitney is chronically late delivering engines for the Pentagon’s costliest program, the F-35, raising questions about whether the company is ready for a surge to full-rate production scheduled for next year.
Pratt remains under a previously unreported “Corrective Action Request” from the Defense Contract Management Agency that cites “poor delivery performance” on its current batch of engines for the fighter jet, including for the most complicated version used by the Marine Corps and the U.K. for vertical takeoffs and landings. Pratt & Whitney is a subsidiary of Farmington-based United Technologies Corp.
Pratt & Whitney president to retire next year as UTC and Raytheon combine in aerospace and defense merger »
The agency’s action is likely to be watched not only by the Pentagon and international buyers of the F-35 but also by shareholders and investors assessing United Technologies’ planned merger with Raytheon Co., which would fortify the combined company’s standing as one of the top U.S. defense contractors.
The F-35 engines would be one of the new company’s top revenue producers. The company, which is the sole supplier of engines for the fighter built by Lockheed Martin Corp., must demonstrate by year-end that it has delivered on promised improvements to solve the problems that led to the agency’s formal request in December, spokesman Mark Woodbury said in a statement outlining the issues.
[Business] City will move forward with Downtown North development after jury backs Hartford’s decision to fire Dunkin’ Donuts Park developer in 2016 »
The $428 billion F-35 program is scheduled for approval next year to enter full-rate production, the most lucrative phase of a weapons program for contractors. The decision is contingent on an assessment during the aircraft’s current round of intensive combat testing that it’s effective and can be maintained.
Of the $428 billion, as much as $66 billion is to be spent on at least 2,470 engines -- designated the F135 -- for U.S. jets, including $53.4 billion in procurement, according to the Defense Department’s latest Selected Acquisition Report on the F-35.
Pentagon budget documents indicate the engine program is valued at about $2 billion annually for Pratt, according to Bloomberg Intelligence analyst Douglas Rothacker.
John Thomas, a spokesman for Pratt, said in an emailed statement that “we take seriously our responsibility to meet F135 production commitments. The corrective action plan submitted earlier this year lays out how we are doing that. Over the past year, we have invested more than $200 million for additional capacity, and currently have over 100 Pratt & Whitney employees deployed to our supplier facilities in support of production obligations.”
Pratt & Whitney President Bob Leduc underscored the engine’s revenue potential to analysts June 17 at the Paris Air Show.
[Business] City will move forward with Downtown North development after jury backs Hartford’s decision to fire Dunkin’ Donuts Park developer in 2016 »
“So another way to think about the F135 is a year ago we made about eight engines a month,” he said. “Right now we are between 13 and 14 engines a month. But when you think about the F135, it’s 16 engines a month for the next 30 years. There will be over 4,000 of these airplanes when it’s all said and done,” including foreign sales.
The primary issues resulting in late engine deliveries “have been related to supply-chain capacity, material shortages” and production issues, according to the contract management agency.
“Engine test failures due to high vibrations and foreign object debris continues to plague” production, the agency said in an internal quarterly assessment for January through March.
Deliveries of the Marine Corps model engines “have been consistently late,” it said.
As of early June, Pratt & Whitney was contractually required to deliver 108 engines in the latest production contract, the program’s 11th. Of the 90 delivered, 88 were “late by an average of 40 days,” Woodbury said in his statement.
The Pentagon is close to finalizing the award of the 12th and largest F-35 contract to date with Lockheed and Pratt.
The current delays add to Pratt & Whitney’s spotty track record. Even as deliveries increased to 81 in 2018 from 48 in 2012, 86 percent of those were delivered late, up from 48 percent in late 2017, according to an April report from the Government Accountability Office.
Asked whether the contract management agency has confidence Pratt will be ready for a full-production decision, Woodbury said the agency is monitoring milestones in Pratt’s corrective action plan and needs to see progress before making that judgment.
The agency’s assessment said that in light of Pratt & Whitney’s track record it believes the company “will encounter issues keeping up with demand for any future low-rate and full- rate production contract” that increases quantities.
https://www.bloomberg.com/news/arti...gies-pratt-slow-on-f-35-engines-pentagon-says
United Technologies’ F-35 Engines Chronically Late, Pentagon Says
By
Anthony Capaccio
July 2, 2019, 4:00 PM GMT+8
- Contract agency questions if contractor is ready for a surge
- A ‘poor delivery performance’ finding remains in effect
LISTEN TO ARTICLE
4:22
SHARE THIS ARTICLE
Share
Tweet
Post
In this article
UTX
UNITED TECH CORP
133.00
USD
+1.04+0.79%
LMT
LOCKHEED MARTIN
370.38
USD
+2.81+0.76%
RTN
RAYTHEON CO
173.45
USD
+0.65+0.38%
United Technologies Corp.’s Pratt & Whitney unit is chronically late delivering engines for the Pentagon’s costliest program, the F-35, raising questions about whether the company is ready for a surge to full-rate production scheduled for next year.
Pratt remains under a previously unreported “Corrective Action Request” from the Defense Contract Management Agency that cites “poor delivery performance” on its current batch of engines for the fighter jet, including for the most complicated version used by the Marine Corps and the U.K. for vertical takeoffs and landings.
The agency’s action is likely to be watched not only by the Pentagon and international buyers of the F-35 but also by shareholders and investors assessing United Technologies’ planned merger with Raytheon Co., which would fortify the combined company’s standing as one of the top U.S. defense contractors. The F-35 engines would be one of the new company’s top revenue producers.
The company, which is the sole supplier of engines for the fighter built by Lockheed Martin Corp., must demonstrate by year-end that it has delivered on promised improvements to solve the problems that led to the agency’s formal request in December, spokesman Mark Woodbury said in a statement outlining the issues.
An F-35
Photographer: Eric Baradat/AFP via Getty Images
Full Production
The $428 billion F-35 program is scheduled for approval next year to enter full-rate production, the most lucrative phase of a weapons program for contractors. The decision is contingent on an assessment during the aircraft’s current round of intensive combat testing that it’s effective and can be maintained.
Of the $428 billion, as much as $66 billion is to be spent on at least 2,470 engines -- designated the F135 -- for U.S. jets, including $53.4 billion in procurement, according to the Defense Department’s latest Selected Acquisition Report on the F-35.
Pentagon budget documents indicate the engine program is valued at about $2 billion annually for Pratt, according to Bloomberg Intelligence analyst Douglas Rothacker.
John Thomas, a spokesman for Pratt, said in an emailed statement that “we take seriously our responsibility to meet F135 production commitments. The corrective action plan submitted earlier this year lays out how we are doing that. Over the past year, we have invested more than $200 million for additional capacity, and currently have over 100 Pratt & Whitney employees deployed to our supplier facilities in support of production obligations.”
Revenue Potential
Pratt & Whitney President Bob Leduc underscored the engine’s revenue potential to analysts June 17 at the Paris Air Show.
“So another way to think about the F135 is a year ago we made about eight engines a month,” he said. “Right now we are between 13 and 14 engines a month. But when you think about the F135, it’s 16 engines a month for the next 30 years. There will be over 4,000 of these airplanes when it’s all said and done,” including foreign sales.
The primary issues resulting in late engine deliveries “have been related to supply-chain capacity, material shortages” and production issues, according to the contract management agency.
“Engine test failures due to high vibrations and foreign object debris continues to plague” production, the agency said in an internal quarterly assessment for January through March. Deliveries of the Marine Corps model engines “have been consistently late,” it said.
As of early June, Pratt & Whitney was contractually required to deliver 108 engines in the latest production contract, the program’s 11th. Of the 90 delivered, 88 were “late by an average of 40 days,” Woodbury said in his statement. The Pentagon is close to finalizing the award of the 12th and largest F-35 contract to date with Lockheed and Pratt.
Spotty Record
The current delays add to Pratt & Whitney’s spotty track record. Even as deliveries increased to 81 in 2018 from 48 in 2012, 86% of those were delivered late, up from 48% in late 2017, according to an April report from the Government Accountability Office.
Asked whether the contract management agency has confidence Pratt will be ready for a full-production decision, Woodbury said the agency is monitoring milestones in Pratt’s corrective action plan and needs to see progress before making that judgment.
The agency’s assessment said that in light of Pratt & Whitney’s track record it believes the company “will encounter issues keeping up with demand for any future low-rate and full-rate production contract” that increases quantities.
— With assistance by Rick Clough
http://www.defense-aerospace.com/ar...the-long-history-of-f_35-engine-problems.html
Home
Releases
Reports
Word for word
Features
AFP News
Order
F-35 Grounded After New F-135 Engine Problems
(Source: JSFNieuws.nl; published February 22, 2013)
By Johan Boeder
There have been several instances of turbine blades breaking off on the Pratt & Whitney F135 engine. Shown here are several broken blades during the first known incident, on Aug. 30, 2007, which ultimately led to the engine’s re-design in 2008. (photo P&W)
KESTEREN, Netherlands --- On Thursday, February 21, 2013, the Pentagon Friday ordered the grounding for all F-35 aircraft, after a routine check at the Edwards Air Force Base revealed a crack in a low pressure turbine blade in the engine of an F-35A.
This is but the latest incident concerning the Pratt & Whitney F135 engine, as during 2007-2009 repeated problems with turbine blades led to significant delays in the test program and a partial redesign of certain parts of the engine.
On February 19, 2013 a routine inspection took place of a Pratt & Whitney F135 engine at Edwards AFB, USA. During the inspection using a borescope, there were indications that there was a crack in a LPT turbine blade. It was confirmed after further investigation. The turbine blade is sent to Pratt & Whitney in Middletown (CT), USA for further investigation.
Statements from JSF Program Office
The F-35 JSF Program Office said in a Feb. 22 statement to the press: “It is too early to know the fleet-wide impact of this finding, however as a precautionary measure, all F-35 flight operations have been suspended until the investigation is complete and the cause of the blade crack is fully understood. The F-35 Joint Program Office is working closely with Pratt & Whitney and Lockheed Martin at all F-35 locations to ensure the integrity of the engine, and to return the fleet safely to flight as soon as possible.”
Lt. Gen. Chris Bogdan, head of the JSF Program Office, suggested in a briefing in Australia that if the crack's cause was as straightforward as a foreign object striking the turbine, or a basic manufacturing defect, “I could foresee the airplane back in the air in the next week or two.”
Bogdan added that “If it's more than that, then we have to look at what the risk is to the fleet,” adding than a verdict on the cracking's cause was expected "by the end of this week", Reuters reported from Melbourne.
Some facts about what happened
It was a F-135 engine with 700 hours, of which 409 flight hours. The aircraft was the F-35A test aircraft AF-2. The half-inch wide crack was found in a turbine blade of the low pressure turbine section. This makes it unlikely that it is caused by so-called FOD (Foreign Object Damage), such as a bird strike, because such an object has to pass the Fan Section (3 stages) Compressor Section (6 stages), combustor and high pressure turbine section before reaching the low pressure turbine section.
Cracks in turbine blades in the low pressure turbine section usually are caused by high thermal or other stressing loads of the turbine blades. The forces in the 40.000 lb (about 29.000 hp) engine are enormous. A grounding after such a discovery usually takes relatively short (e.g. one week), normally a manufacturing error or some incident is the root cause.
Until then, for safety reasons a grounding may be the standard procedure. Reuters reported Feb 24 that “In fact, two jets were airborne at air bases in Maryland and Arizona and had to be recalled, said one of the sources.” At this moment, all 51 F-35s, of all versions, in use at several airfields to support the test and training program, are grounded.
Long history of engine problems since 2006
It cannot be excluded that the root cause of the current problem is more structural than a simple manufacturing error or an isolated incident. Since 2006 there had been a series of engine problems with the F-135 engine.
In May 2006, Aviation Week reporter David A. Fulghum wrote a detailed article “Joint Strike Fighter F135 Engine Burns Hotter Than Desired” and described the risk of a shorter engine life or engine damage caused by higher than expected temperatures on the F-135 engine.
In August 2007 and February 2008 there were serious problems. Turbine blades broke off suddenly by a form of metal fatigue. The cause was sought in a combination of factors.
On 30 August 2007 in test engine FX634, after 122 hours of testing, a turbine blade in the 3rd LPT stage broke off completely. On February 4, 2008 something similar happened to engine FTE06, also in the 3rd LPT stage, after 19 hours.
These problems with the engine contributed significantly to the delays in the JSF test program for the period 2007-2008.
Redesign of the engine in 2008
In early 2008, an engine, the FX640 ground test engine, was equipped with numerous sensors and instruments. On April 21, 2008 a test process was started to find the cause of the problem. Through a detailed test plan the forces and tensions that arise in the engine were mapped in different power ranges.
At that moment it seemed to be primarily an issue of the F-35B STOVL (vertical landing) version. The cracks in the turbine blades were created in exactly the same place, and seemed to occur when switching from forward to vertical drive. Later in 2008, the results became available. The blade cracks seemed to have been caused by certain vibrations that triggered a material failure.
This led to a redesign of a number of elements in the engine. One of the upgrades was a change of the distance between the turbine blades. After the redesign the engine was retested and recertified. At the end of 2008 Pratt & Whitney issued a press statement, saying that they were convinced that the problems were solved.
(UPDATE: A link to a July 22, 2008 briefing by Pratt & Whitney on F135 blade failures was removed on Feb. 28 at the request of the F-35 Joint Program Office. The "information in those slides has the potential to compromise the safety of our pilots," the request stated -- Editor.)
In 2009, problems with redesigned engine
In July 2009, the then head of the JSF Program Office, Marine Corps Maj. Gen. David R. Heinz, was still was not happy with the F-135 problems. He told the press: “The problems include too many individual blades that fail to meet specifications, as well as combined “stack-ups” of blades that fail early. I’m not satisfied with the rates that I’m getting.”
A few days later he was ordered by the Pentagon not to comment publicly on problems with the F-135 engine.
In September 2009, serious engine problems were again revealed during testing of the Pratt & Whitney F-135 engine. At a crucial moment in the debate in the U.S. Congress on the choice of two competing engine types (the Pentagon wanted to axe the alternate engine (the GE / Rolls Royce F-136), a Pratt & Whitney F-135 engine broke down. Again, the cause seemed to lie in broken turbine blades. However, this time the same problem occurred in the new, redesigned engine with redesigned turbine blades.
Engine problems continue until now
After the problems in 2009, officials no longer publicly commented about the engine problems. Also there were no indications that there actually were problems with the engine or that there were any reliability issues.
In April 2011, however, Admiral Venlet, the then Head of JSF Program Office, told reporters that some engine problems were impacting on the delivery schedule.
The grounding last week puts the engine back in the publicity spotlight. However, this time it is not the complex F-35B STOVL version, but the much simpler engine in the F-35A, the Air Force version, that failed, which has led some observers to speculate that the problem could be more deeply ingrained in the engine’s design.
History of previous F-35 groundings
May 2007: The first incident was recorded in May 2007, when the F-35A prototype AA-1 experienced an electrical short that disabled flight controls on the horizontal stabliser. A grounding was ordered and continued until December 2007, due to time needed to redesign several parts of the 270-volt electrical system and F-135 engine problems.
July 2008: On July 23, 2008, both flying F-35 prototypes were grounded after problems were detected with ground cooling fan electrical circuitry, DCMA reported on Aug 18, 2008 that tests were delayed as a result of testing anomalies on the 28 Volt and 270 Volt Battery Charger/Controller Unit, the Electrical Distribution Unit and the Power Distribution Unit. It was due to design problems. Flights were resumed first week of September-2008.
December 2008: On Dec 12, 2008 the F-35 was grounded again as a result of engine and ejection seat anomalies. Seat anomalies were observed in ejection seat sequence during an escape system test on Nov. 20, 2008. It took nearly 3 months to solve the problems and aircraft AA-1 did not return to the skies until Feb. 24, 2009.
May 2009: The F-35 fleet didn’t fly between May 7, 2009 (84th flight of prototype AA-1) and Jun 23, 2009. No comments were available from JPO or L-M.
October 2010: F-35 fleet grounded after the fuel pump shut down above 10,000ft (3,050m). The problem was caused by a software bug.
March 2011: The entire F-35 fleet was grounded some weeks after test aircraft AF-4 experienced a dual generator failure. After both generators shut down in flight, the IPP activated and allowed the F-35’s flight control system to continue functioning. The problem was traced to faulty maintenance handling.
June 2011: Carrier-based F-35C suspended from flying after engineers at NAS Patuxent River discovered a software problem that could have affected the flight control surfaces. Grounding was from 17 June until 23 June, 2011.
August 2011: A precautionary grounding of all 20 F-35s that had reached flying status was ordered Aug. 3, 2011 after a valve in the Integrated Power Package (IPP) of F-35A test aircraft AF-4 failed. On 18 August 2011 the flight ban was lifted to allow monitored operations. A permanent resolution would be installed later.
January 2012: 15 Lockheed Martin F-35s are grounded for about 12 days to repack improperly installed parachutes (reversed 180 degrees from design). The grounded aircraft are equipped with new versions of the Martin Baker US16E ejection seat, designated as -21 and -23.
January 2013: The F-35B STOVL variant was grounded Jan 18, 2013 after detection of a failure of a fueldraulic line in the aircraft's propulsion system. The Pentagon cleared all 25 F-35B aircraft to resume flight tests on February 12, 2013. Problem caused by a manufacturing quality problem (wrongly crimped fuel line).
February 2013: On Feb. 21, 2013, the Pentagon ordered a grounding for all F-35 aircraft, after a routine check at the Edwards Air Force Base revealed a crack in a low pressure turbine blade in an engines of a F-35A.
-ends-